The old floor and tiles have been ripped out, and the relocated electrical and plumbing roughed in. In the last few days, the contractor installed the new subfloor and finished and painted all the walls and ceiling. The bulkhead that ran along the length of the wall above the old cabinets has been virtually eliminated, with only a small plumbing vent that ran through it remaining in place. It’ll be hidden inside the new cabinets.
The new cork floor is to follow this week, with the cabinet installation scheduled for Thursday and Friday. Sometime after that, we get our appliances, counter, and sink. With any luck, we’ll be fully kitchened again on schedule by mid-September. With even more luck, the worst of the dust is behind us.